A CLOSER LOOK
/MAJOR MULTI-YEAR PROJECTS IMPACT WEST END COMMUTE
City considering traffic calming on Thurlow
by John Streit
(click images to enlarge)
Whether you walk, roll, drive, or take transit in the West End, you may have felt the impact of two major infrastructure projects currently affecting street and sidewalk traffic in our neighbourhood. Drivers are being diverted into already tight laneways and pedestrians are sometimes forced to choose different paths to get home or go to work as they maneuver temporary ramps, orange pylons, and flag persons.
TELUS AND BC HYDRO WORK ON BUTE AND NELSON. (BC HYDRO GRAPHIC)
The 1100 block of Nelson Street between Bute and Thurlow remains closed as BC Hydro contractors work on the West End Substation Project. Official notice of construction was given for November 30th but that stretch of Nelson had been closed for weeks prior with pre-work happening at Nelson Park and Roberts Annex.
BC Hydro says one crew will work on Nelson Street, installing power line housing underground, and a second crew will install fencing and deliver and remove materials to the substation site from 7 a.m. to 8 p.m. On the West End Substation Project website (see “Related Links” below), Hydro says work will include “duct bank and vault installation in the roadway, excavating the road, installing pre-made vaults (concrete rooms) and conduit (plastic pipes), refilling the excavations and restoring the road.” This as a TELUS contractor continues its work to build new underground cable housing to by-pass Nelson Park at Bute and Nelson. That work will be done in early 2027. Onsite crews and signage will direct people travelling around the work zone and traffic signs have been posted.
A few blocks south on Davie Street, City of Vancouver upgrades continue there between Bute and Broughton. Sidewalks are being replaced and widened, trees cut down and replaced and new infrastructure is being installed. This work is scheduled to continue until Spring 2028. You can read more about the Davie Village upgrades in the October edition of the West End Journal (see “Related Links” below).
For more about these two projects and other 2027 roadwork projects in our neighbourhood, The West End Journal (TWEJ) reached out to the City of Vancouver.
Here’s our Q & A:
Q: The West End Journal has been hearing about much busier laneways near Nelson Park as work continues on the Hydro substation project. Any plans to better manage traffic through laneways?
A: The City recognizes the traffic and access challenges that come with having multiple utility and development projects underway in the West End at the same time.
We will continue to work with project teams and contractors to address concerns and look for opportunities to minimize impacts on residents, businesses, and people travelling through the neighbourhood.
WEST END SUBSTATION PROJECT CONSTRUCTION CLOSURE OF NELSON STREET.
The West End is a traffic-calmed neighbourhood, so there are limitations to how much traffic can be redirected onto local streets and laneways. We also need to balance traffic management with the needs of businesses and commercial vehicles that rely on laneways for deliveries and access. Adding too many restrictions or traffic control measures could create challenges for these users as well.
Many of the current impacts are temporary and will change as projects move through their various phases. We will continue to work with the project teams to manage these impacts as best we can while balancing construction needs, neighbourhood livability, and access for all road users.
Additionally, any specific concerns or questions regarding the BC Hydro substation project can be directed to westendsub@bchydro.com or by calling 604-341-1304.
Q: How is work progressing on the Davie Street Upgrades?
DAVIE STREET UPGRADE CONSTRUCTION WORK.
A: The Davie Village Upgrades Project is progressing on schedule, with total project completion expected in spring 2028. The project has complicated sequencing of work requiring shifting of construction work zones periodically. We are currently working on widening the sidewalks on the north side of 1200-block and will move to the south side at the end of November.
Q: Any changes in response to business concerns on Davie Street?
A: The project team is in regular contact with the West End business community and continues to consider feedback as the project moves forward. We recognize the importance of minimizing impacts on local businesses and are looking for opportunities to support them wherever possible, including through wayfinding and business access signage, maintaining access for customers and deliveries, and clear communication about construction activities and timelines.
Q: What is some of the other street/sidewalk work happening in the West End in 2027?
A: Approximately 4-5 km (about 35-40 blocks) of local (residential) roads are scheduled for repaving in the West End in 2027. No arterial or major road network paving, or sidewalk rehabilitation, is planned in the West End in 2027 beyond the Davie Village upgrades work.
Q: Any new traffic calming measures (like yellow concrete barriers installed in East Vancouver) or added stop signs/traffic circles coming to the West End in 2027?
A: The City is looking at improving Burnaby Street, between Burrard Street and Bute Street, with a focus on the Burnaby Street at Thurlow Street intersection. Burnaby Street is a local bike route that connects to key destinations in the West End. As part of this work, some traffic calming measures are being considered to reduce vehicle volume on this portion of street.
EXTRA TRAFFIC CALMING BEING CONSIDERED FOR THURLOW AND BURNABY.
Q: Nelson Street continues to be top of mind for residents in terms of dangerous pedestrian crossings. Any plans to install zebra crossings or flashing warning lights at tricky intersections including Bidwell and Nicola?
A: The City receives hundreds of requests for crossing upgrades, so we follow a warrant-based approach to determine which intersections have priority each year. Staff will continue to assess intersections city-wide, including along Nelson Street, to determine if it should be prioritized for additional zebra crosswalks. Signalizing a crossing through flashing lights or a pedestrian or bike-actuated signal is costly. These are typically only reserved for improving crossings over a collector or arterial street. As Nelson Street is a residential street, it will be unlikely to have signalized crossings as other locations are higher in priority. However, all potential candidates will remain in our database for future year's signal programs.
NO CHANGES PLANNED FOR NELSON AND NICOLA INTERSECTION.
Q: Has all the new speed limit signage been installed in the West End?
A: The Neighbourhood Slow Zone signage, including 30km/h speed limit signs, are being installed across a total of 25 Vancouver neighbourhoods over the next few years. Most of the West End neighbourhoods that are a part of this plan will have their signage in 2027.
Q: Any planned changes or improvements to the Beach Avenue Bikeway?
A: Not at this time.